The work at Coppice is to repair the leaks in the far bank and to repair and prevent further erosion to the dam. The leak repair work has been carried out initially and pictures are shown below;
Cutting a channel where piling is to be put
Piling being installed
When the piling install is finished the ditch will be filled covering to top of the piling sheets.
Size of piling sheets used.